[ WAA Home | ProjeX Home | Download ProjeX | Help using ProjeX | ProjeX FAQ | About WAA]Earliest Start TimeWe need to find the earliest start date for each of the nodes. For the first first node (the start of the project) this is our start date. The next node is the earliest start of the previous node plus its duration and so on through the project to give : What next? |