Shop at Amazon.com

[ WAA Home | ProjeX Home | Download ProjeX | Help using ProjeX | ProjeX FAQ | About WAA]


Example - PERT analysis

We saw in a previous example how to use ProjeX to build a schedule for a project that has dependencies between tasks - i.e. one task cannot start until another task has finished (or perhaps can only start after another has started) and then produce a plot to show the critical tasks. In this example we will take this one step further and use PERT to calculated expected task durations and generate a critical path plot based on these estimates.

For this example we will use a simple building project (taken from Quantitative Analysis for Management) to put an A/C unit in a factory.

Task ID Task Description Prerequisites Optimistic
Duration
Most Likely
Duration
Pessimistic
Duration
1 Build internal components none

1

2

3

2 Modify roof and floor none

2

3

4

3 Construct collection stack 1

1

2

3

4 Pour concrete and install frame 2

2

4

6

5 Build high-temperature burner 3

1

4

7

6 Install control system 3

1

2

9

7 Install air pollution device 4, 5

3

4

11

8 Inspection and testing 6, 7

1

2

3

Let's say we want the project to start (the building of the internal components) on May 26th, we can enter the tasks and durations in ProjeX having created a new ProjeX sheet in the standard way to get:

We can set the dependencies between tasks using the table above (in the same way as the previous example).

One point that must be stressed at this stage is that any task with a user specified starting date that is not set relative to another task is thought of as a critical task that must start on the date given.

What do we mean by this? For the 2nd task in the project, its starting date is not dependent on any other task just the date we start the project on. If we type the starting date for the task as 5/26/03 , ProjeX will think that it is a critical path and always treat it as such. We recommend the user define a milestone 'Start the project' as the first task in the list and then set the start date of any tasks that can begin on day 1 to be equal to the milestone start date. For our example this would give:

This way ProjeX will calculate how much 'float' there is for the tasks.

We now need to set the range of durations we expect for the tasks so we can calculated the expected duration ...


Search this site powered by FreeFind


Copyright Mike Witcombe of WAA, 1996-2004.  This page was last updated on July 07, 2004
Please review our privacy policy.
For problems or questions regarding this web site contact [products@waa-inc.com].