I
try to allocate a resource to a task and get the message
"Not a ProjeX task"
There are two possible problems :
- When you use the right mouse the cursor must be
over a task on the ProjeX sheet.
- With versions of ProjeX prior to 97.0.10.1 a
Gantt chart needs to be produced for ProjeX to
'see' more than the number of tasks originally in
the sheet.
This means just generate a Gantt chart on that ProjeX
sheet and then try again. This quirk has been corrected
for later versions of ProjeX.
Can
I mix resource time definitions in one project?
With versions of ProjeX prior to 97.0.11 the short
answer is no. The problem is not the allocation itself
but the plotting of the resources. With the earlier
versions of ProjeX a given resource needs to use the same
time definition type for each of the tasks allocated to
it.
With the latest versions of ProjeX you can mix and
match percentage allocations with hours or days as
required.