Using task dependencies with ProjeX

After I reset the ProjeX sheet the task dependencies are no longer functional

ProjeX only uses the dependencies for the actual Gantt plotting if you tell it to in the 'Display Parameters' dialog.

When you do the reset it sets the default for using the dependencies back to off. Under the General tab of 'Display Properties' there is an option to 'Use dependencies for task start dates'. Select this and it will use the dependencies you have set to draw the Gantt chart and also, when you bring up the 'Set dependencies' option, by default the 'Update using dependencies' box will be checked.