The problem is not with the number of tasks but the
duration of the project and time axis you are using.
Under "ProjeX Properties" select "Gantt
Chart Display Properties", set the Display time axis
to weekly and you should be able to add the extra tasks.
Later versions of ProjeX automatically switch to the
next time axis 'up' (not available with the freeware
version).
I
want to change the way tasks are calculated but ProjeX tells
me I can't
A lot of task manipulation is now handled from the 'Task Definition' option, this is
one of them.
I
changed the way ProjeX calculates tasks and now I have
'circular references'
Earlier version of ProjeX allowed the user to generate
a ProjeX sheet with tasks defined by the start date and
duration and then change this to start and end dates.
This led to circular references. These circular sheets
can be recovered.
See the above answer for how you are meant to
change
the way tasks are calculated.
How do I create
milestones ?
1. If you are calculating tasks based on start date
and duration (the default) then simply set the duration
of the task to zero.
2. If you calculating tasks based on start and end
then leave the end date blank.
Alternatively use the 'Task
Definition' option.