|
[ WAA Home | ProjeX Home | Download ProjeX | Help using ProjeX | ProjeX FAQ | About WAA]Work Week options of the Display Dialog
Dates to exclude from the schedule By checking the Weekends box, weekends will be marked as "non-work" days when the Gantt chart is generated. Weekends can now be defined as lasting more than two days and they do not need to be consecutive. There are three ways of handling tasks if weekends are excluded from the 'work week'. Let's take the following example below: If we select the 'Adjust tasks' option the durations is taken to mean the actual worked days and the ending date of tasks are updated to allow for the weekends (e.g. for Task 1 the end has been changed from June 28th to July 2nd). Also note that the starting dates of any tasks related are updated (e.g. Milestone 1 which is dependent on the end of Task 1 now starts on July 3rd).
Weekend Definition The definition of the 'weekend' varies throughout the world. The user has the ability to select the days of the weeks that are to be considered the weekend. Weekend can now be two days or more (not necessarily consecutive). This can now be set on a task by task basis using the 'Task Definition' option from the right mouse button menu.
Plotting the Gantt bar through the weekend This option is used to draw the Gantt bar through the weekends while still adjusting the task start/end dates and duration (as set by the user) for the task not to actually be worked on over the weekend.
|