Shop at Amazon.com

[ WAA Home | ProjeX Home | Download ProjeX | Help using ProjeX | ProjeX FAQ | About WAA]


Inserting a new task using the right mouse button.

Using the right mouse button to select a task,

The following dialog appears:

Initially we need to decide whether to insert the new task above or below the current task. Then we can make the new task dependent on the task above and the task below it (the start of the new task will be dependent on the end of the task above and the start of the task below dependent on the end of the new task) or we can just make the task dependent on the task above or the task below dependent on the end of the new task. As a final option we can just insert the new task and not modify any of the dependencies.


Search this site powered by FreeFind


Copyright Mike Witcombe of WAA, 1996-2004.  This page was last updated on July 07, 2004
Please review our privacy policy.
For problems or questions regarding this web site contact [products@waa-inc.com].